Aker Solutions’ SeaBooster™
At the end of 2008, the manufacture of the three pumps was completed and they were transported from Aker Solutions’ facility at Tranby, Norway, to Horten where they underwent installation testing.
At the heart of the SeaBooster™ system for Tyrihans will be two LiquidBooster™ centrifugal pumps, a design evolved from Aker Solutions’ long-established proprietary pump technology for exporting crude oil and pumping produced water.
The pump system will be installed in 270 metres water depth approximately 31 kilometres from the Kristin platform. Both the tested pump duty of 2.7 megawatt and the 31 kilometre step-out represent new world records for subsea pumps.
The pumps will draw in 14 000 cubic metres of untreated seawater each day, injecting it into the sea bed between the oil reservoirs Tyrihans North and South. When this is combined with gas injection, optimal pressure support is obtained in the reservoir and a higher degree of oil recovery and production is achieved.