Statfjord C

Statfjord C was installed in June 1984 and started production in 1985. The platform is connected to satellite subsea wells in the north and east. The base has 4 shafts, 24 cells, oil storage and provides facilities for drilling, production and accomodation.

Description

Condeep 4 / 24. PDQ, Storage

Construction site

Stavanger, Norway

Installation site

The Statfjord field, the North Sea

Topside, operating weight

52 000 tonnes

Total weight of structure

643 700 tonnes

Total height of concrete structure

175 m

Total height of platform with deck

290 m

Concrete

126 000 m3

Topside production capacity

300 000 bopd and 6500 million Sm3/d

Storage capacity

1 900 000 bbl

Well slots

42

Topside installation on substructure

February 1984

Tow to field / installation on field

June 1984

Copyright statement

All contents of this Site including without limitation the design, layout, graphics, photos, format, and other visual elements of the Site are protected by intellectual property rights, including but not limited to Copyright © 2011 Aker Solutions ASA (or where so indicated, any affiliates of Aker Solutions ASA or its licensors). Any rights not expressly granted herein are reserved. All ownership rights pertaining to the information and material contained on this Site, including but not limited to the Aker Solutions name, logos, trademark, graphics, photos, images, and content, are owned or have been duly licensed by Aker Solutions ASA (or any of its affiliates), WITH ALL RIGHTS RESERVED.